We would like to take this opportunity to thank you for all your co-operation during the balcony repairs.

Please be advised that it has been very difficult to provide you with prior updates due to the scope of work being more extensive than originally anticipated but we are happy to inform you that all major crushing and chipping have been completed other than minor chipping required on the east side of the building.

Therefore, although conservative please be advised of the following updated schedule provided by our Engineer and Contractor:

North Elevation – before Christmas 2014
South Elevation – end of January 2015
East Elevation – end of February 2015
West Elevation – end of February 2015

Our Contractor's goal is to complete the work as early as possible weather permitting.

We would like to apologize for the inconvenience and thank you for your co-operation in the above matter and on behalf of all staff at Wilstar Management we wish you and your families a safe, healthy and happy holiday season.